Milling and Paving of John Paul Road, Municipal Drive, and Merchant Row

The City is initiating some milling and overlay roadwork during the next few days. Milling is a process where top layer of asphalt pavement is ground up and removed. Then, a “binder” is added to the left-over road surface (which is acts like glue) and a new layer of asphalt is added on top of the binder. This process is important in extending the useful life of the subsurface of the road structure. For those who might be interested, here’s a YouTube video that demonstrates the mill and overlay process: http://www.youtube.com/watch?v=yy1tWWHvV-w.

Milling will take place on John Paul Road, Municipal Drive, and Merchant Row on Wednesday and Thursday of this week (October 7th and 8th). There will be temporary traffic delays.

Paving is expected to occur, weather permitting, on Monday and Tuesday next week (October 12th and 13th). Temporary road closing will occur during the paving process.

Thanks to everyone for your patience and attentive driving in and around these project areas.