Please see below for a summary of upcoming construction activities that will be occurring on Janesville Street / Milton Road / BUS. 26 - (E. Madison Ave and CTH N) and High Street / Old STH 59 - (Janesville St. - STH 59) in Rock County. The summary of activities is preliminary and may change based on weather and other site conditions.
The schedule for the week of October 27th includes:
Thanks,
Brandan L. Hager, P.E.
WisDOT Sr. Civil Engineer- Transportation
DTSD SW REGION - Madison, WI
brandan.hager@dot.wi.gov
- Janesville Street/Milton Road is Closed To Through Traffic, Local Access Only. Please use alternate routes if at all possible.
- The Otter Creek bridge is closed as of 9/2/14, and will remain closed until the bridge work is completed.
- Continued work on the Otter Creek bridge deck replacement.
- Beam guard installation is scheduled for the STH 26 (old) project.
- John Paul Road (McCormick Dr. to STH 26) will be closed to through traffic starting October 20th,2014.
- Asphalt paving of intersections and driveways are scheduled to be done over the STH 59 Old project.
- Asphalt paving of High Street (Storrs Lake to STH 59) and John Paul Road (McCormick Dr. to STH 26) is scheduled.
- Please anticipate construction traffic and single lane closures/flagging operations on the High street portion of the project for asphalt paving construction.
- Shouldering, Pavement Marking, and sign installation is scheduled for the entire project.
Thanks,
Brandan L. Hager, P.E.
WisDOT Sr. Civil Engineer- Transportation
DTSD SW REGION - Madison, WI
brandan.hager@dot.wi.gov