Friday, October 31, 2014

Update on Road Construction on Janesville Street and High Street - October 31st

Below is an update on the road construction taking place on Janesville Street and High Street.



Good Morning,

Please see below for a summary of upcoming construction activities that will be occurring on Janesville Street / Milton Road / BUS. 26 - (E. Madison Ave and CTH N) and High Street / Old STH 59 - (Janesville St. - STH 59) in Rock County. The summary of activities is preliminary and may change based on weather and other site conditions.

The schedule for the week of November 3rd includes:
  • The Otter Creek bridge is closed as of 9/2/14, and will remain closed until the bridge work is completed. 
  • Pavement marking on bike path portion of the project. 
  • Shouldering near Otter Creek Bridge. 
  • Restoration, topsoil and seeding across the project. 
If you are aware of any others that would like to be included on these updates, or if you would like to be removed, please contact me at brandan.hager@dot.wi.gov or stop by the field office located at 1141 E. High Street in Milton. The field office phone number is (608) 868-2055.

Thanks,

Brandan Hager, P.E.
WisDOT Sr. Civil Engineer- Transportation