Mainline paving is progressing and should be completed next week. After this, there is still ramp paving and all the tie in work to the bridges. The contractor assumes another 3 weeks of concrete work. After that, HMA paving, beam guard, shoulders, signs, rumble strips, etc. will be worked on. Late August +/- is still the schedule to open the bypass to traffic.
Work on the STH 59 roundabouts is scheduled to begin on July 8th and go until July 26th +/-. STH 59 will be detoured utilizing High Street (Old STH 59) just like last year when work was done at the interchange. Message boards will go up as a pre-warn closer to the end of the month.