Monday, June 24, 2013

STH 26 Bypass Project Update

Mainline paving is progressing and should be completed next week. After this, there is still ramp paving and all the tie in work to the bridges.  The contractor assumes another 3 weeks of concrete work. After that, HMA paving, beam guard, shoulders, signs, rumble strips, etc. will be worked on. Late August +/- is still the schedule to open the bypass to traffic.

Work on the STH 59 roundabouts is scheduled to begin on July 8th and go until July 26th +/-. STH 59 will be detoured utilizing High Street (Old STH 59) just like last year when work was done at the interchange. Message boards will go up as a pre-warn closer to the end of the month.